Essential KPIs Every Contractor Needs to Assess Monthly: A One-Page Scorecard

A monthly KPI scorecard for construction companies: ten numbers with a target and owner, a 45-minute review, and how to use it to choose more profitable work.

Contractors Advisory
A hand points at a 70% gauge on a printed report full of colorful charts held on a clipboard

A KPI scorecard is one page with the same handful of numbers every month, each with a target and a person who owns it. For a construction company, the useful KPIs are the ones that lead to a decision: which work to chase, which job type to reprice, which crew needs help, whether you can afford to grow. Ten numbers reviewed every month beat thirty numbers nobody looks at.

This guide gives you a ten-KPI scorecard for contractors, how to calculate each number, a worked example, a 45-minute monthly review, and how to use the scorecard to choose better work.

Why a long KPI report doesn’t help

A report with a lot of numbers on it often doesn’t change anything, because:

  • There’s no target, so nobody knows whether 31% is good or bad.
  • There’s no owner, so a number going the wrong way is everyone’s problem and nobody’s job.
  • It’s revenue-heavy. Revenue tells you how busy you were, not whether being busy was worth it.
  • It isn’t reviewed on a fixed day, so it gets looked at when something already feels wrong.

A scorecard fixes all four: few numbers, a target for each, an owner for each, the same meeting every month.

The ten KPIs

# KPI How to calculate it What it tells you Suggested owner
1 Revenue: booked and collected Signed work this month; cash received this month Whether sales and collections are keeping up with the work Owner
2 Gross margin (Revenue − direct job costs) ÷ revenue, on jobs closed this month Whether you’re pricing and running jobs well Owner or operations manager
3 Margin variance Actual gross margin − estimated gross margin, on jobs closed this month Whether jobs finish at the margin you bid Estimator
4 Gross profit per crew hour Gross profit ÷ crew hours, by job type Which work makes the most of your limited crew time Owner
5 Backlog Signed work not yet done, in crew-weeks How far ahead your crews are booked Sales or owner
6 Close rate Proposals signed ÷ proposals sent, by count and by value Whether you’re quoting the right work at the right price Sales or estimator
7 Days to invoice Days from work finished to invoice sent, averaged How fast closeout turns into billing Office
8 Receivables over 30 days Total unpaid invoices more than 30 days past their date Money you’ve earned but can’t use Office
9 Cash low point The lowest balance in your 13-week cash flow forecast Whether you can afford what’s coming Owner
10 Rework hours Rework and callback hours ÷ all labor hours Quality, and a margin leak you can measure Operations or crew leads

A few notes:

  • Gross profit per crew hour is worth tracking. Crew time is the thing you can’t easily buy more of. Construction job costing shows how to calculate it.
  • Backlog in crew-weeks, not dollars. “Eleven crew-weeks of signed work” tells you whether to sell harder or slow down. “$410,000 of backlog” doesn’t.
  • Targets are yours. Set them from your own numbers: your required gross margin from construction profit margins, your minimum cash balance, your own past close rate.

Service-heavy businesses (HVAC, plumbing, electrical service) can swap one or two for first-time fix rate (jobs finished on the first visit ÷ all jobs) and repeat customer rate. For financial ratios like receivables turnover and debt-to-equity, see essential financial KPIs for contractors.

Example scorecard

A three-crew remodeling company. All numbers are made up to show the format. Green is on target, Amber is slightly off (watch it), Red is clearly off and needs an action this month.

KPI Target Last month This month Status Note
Revenue booked / collected $190k / $180k $205k / $172k $176k / $194k Amber Booking dipped; collections caught up
Gross margin 30% 29.4% 27.8% Red Two deck jobs well under
Margin variance −1 pt or better −2.1 pts −4.0 pts Red Same two decks: labor over estimate
Gross profit per crew hour $40 $41 $37 Amber Pulled down by the decks
Backlog 8–12 crew-weeks 11 9 Green
Close rate (by value) 35% 38% 31% Amber Lost two large kitchens on price
Days to invoice 2 3 5 Red Timesheets late on three jobs
Receivables over 30 days under $15k $21k $12k Green
Cash low point (13 weeks) over $40k $52k $38k Amber Dip in week 7: insurance renewal
Rework hours under 3% 2.6% 3.4% Amber Cabinet install errors on one job

The meeting skips the green rows and spends its time on the reds: the two deck jobs behind both margin rows (estimate or field?) and the late timesheets behind days to invoice. The amber cash low point gets a quick look too: the insurance renewal in week 7 needs planning.

Use the scorecard to choose better work

Once a quarter, break gross margin, gross profit per crew hour and close rate down by job type. Example numbers, made up:

Job type Jobs Gross margin Gross profit per crew hour Close rate Decision
Bathrooms 14 34% $52 41% Market more; raise prices slightly
Kitchens 6 29% $44 22% Review why the large bids are being lost
Decks 9 22% $31 48% Reprice: winning half of all bids at this margin suggests the price is too low
Small repairs 31 38% $18 70% Set a minimum charge, or refer them out

Two things stand out. Small repairs have the best margin percentage and the worst use of crew time, because travel and set-up eat the hours. And decks are winning too often at too low a margin, which points to a pricing problem, not a sales success.

That’s how a scorecard changes what you sell: not “more revenue,” but more of the work that makes the most of your crews.

Run a 45-minute monthly review

Same week every month, with the people who own the numbers.

  1. Before the meeting (owners of each KPI): fill in this month’s number and a one-line note. Nobody fills in numbers in the meeting.
  2. 10 minutes: the scorecard. Read it top to bottom. Skip the greens.
  3. 20 minutes: the reds. For each one: what caused it, one action, one owner, a date.
  4. 10 minutes: last month’s actions. Done, not done, did it work?
  5. 5 minutes: one decision about the work you take on. Chase, reprice, stop or refer out one type of job.

Keep the actions and check them next month. A scorecard without follow-up is a report.

Common mistakes

  • Too many numbers. Start with these ten or fewer. Add one only when you drop one.
  • Numbers that arrive late. If job costs and timesheets aren’t in until weeks after the job, the scorecard is always a month behind.
  • No targets. A number with no target can’t be red or green, so it never triggers a decision.
  • Judging people by numbers they don’t control. The estimator owns margin variance, but the cause may be in the field. Use the review to find out, not to blame.

Your next action

  1. Copy the ten KPIs into a one-page sheet. Cut any that don’t fit your business.
  2. Set a target for each from your own numbers, and name an owner.
  3. Fill it in for last month, then hold the first 45-minute review.
  4. Next quarter, add the job type breakdown and make one decision about your work mix.

What to review: the reds each month, and whether last month’s actions moved them.

Next course: build a sales process your team can run without you.

FAQ

What KPIs should a construction company track?

The ones that lead to decisions: booked and collected revenue, gross margin, actual vs. estimated margin, gross profit per crew hour, backlog in crew-weeks, close rate, days to invoice, receivables over 30 days, the low point in your cash forecast, and rework hours. Ten is plenty.

What is a KPI scorecard?

A one-page table of your key numbers with a target, this month’s result, last month’s result and an owner for each. It’s reviewed at a fixed meeting every month, and anything off target gets an action.

How often should contractors review KPIs?

Monthly for the scorecard, quarterly for the breakdown by job type. Cash is the exception: look at your cash forecast every week.

How many KPIs should I track?

As few as you’ll actually act on. Start with eight to ten. If a number never leads to a decision, drop it.

Where MotionOps helps

In MotionOps, several of these numbers come from work you’re already recording:

  • Job Costing: each job’s revenue compared with its actual labor and material costs, with its profit margin.
  • Business Units & Job Types: assign job types to proposals and work orders for revenue reporting by type of work.
  • Advanced Reporting: compare booked and collected revenue for the timeframe you select.
  • Billing Metrics: see how many invoices are outstanding.
  • Financial Reports: payouts, invoices, revenue, taxes and lead source performance.
  • Team Reports: leaderboards for account managers, project managers and technicians.

See plans and pricing, or try MotionOps free.

Sign Up for 14-Day Risk-Free Trial

Start Free Trial